Friday, 26 April

Akufo-Addo OK with Pokuase Interchange works

Politics
President Akufo-Addo inspecting work on Pokuase Interchange

President Nana Addo Dankwa Akufo-Addo, on Monday, 2 December 2019, expressed satisfaction with the progress of work taking place on the Pokuase Interchange.

With the project commencing in April 2018, and the interchange originally proposed as a 3-tier single-point urban interchange, the contractor, after undertaking a value-engineering assessment, proposed to construct a 4-tier stack interchange, which was approved by the Ministry of Roads and Highways.

Thus far, road works, including drainage and pavement works are far advanced, with most of the local roads identified for construction being concluded.

Additionally, some extra routes, which became necessary after a review of the works are currently far advanced, and will be completed before the end of 2019, with over 10 kilometres of local community roads being completed within the catchment area of the interchange.

The contractor, Zhongmei Engineering Group Ltd., indicated that 4 kilometres of asphalted dual-carriageway have been completed for the Awoshie section of the project, with landscaping and street lighting works underway as well as the mounting of road signs and pedestrian facilities.

Also, a kilometre of asphalted single-carriageway has been completed for the Kwabenya section of the project, with pedestrian facilities, and retaining wall constructions being undertaken.

The supervising engineer on site told President Akufo-Addo that drainage works, retaining walls, and earthworks are being constructed on the Accra-Kumasi links to the interchange, in addition to the 2.8 kilometres of outfall storm drains constructed as part of the project to date.

Touching on the interchange itself, the engineer revealed that 99% of pile foundation works has been completed. He said 54% of all pile caps completed; 28% of piers completed; 20% of bridge abutment completed; and 5% of bridge deck under construction.

He also noted that GRIDCo’s 330 kv transmission line has been relocated, and 98% of ECG’s network, which was impacted by the project, has also been relocated. Also, about 400 metres of GWCL 300mm water mains have been relocated.

Dome Kwabenya

At Dome Kwabenya, President Akufo-Addo inspected ongoing works on the 5.5 kilometre Kwabenya Roundabout to Taifa road.

This project was awarded in October 2017 to M/s. GHACOS Limited. The contract sum is GHS 37,457,021.43. It is being funded by the Road Fund.

The scope of work involves the construction of 2.6 kilometres of road from the Kwabenya Roundabout to Taifa Nkatie Burger Junction; comprising 1.6 kilometres of a dual-carriageway merging into a 1-kilometre single-carriageway. It also involves the construction of the 4.3-kilometre section of the Dome-Kitase road with associated drainage works.

Thus far, the 2.6-kilometre road from Kwabenya Roundabout to Taifa Nkatei Burger junction is substantially completed with 300 metres of the 2.5m x 4.2m drain in place. The construction of an outfall storm drain of varying sizes from 1.5m x 1.5m to 1.5m x 2.5m to logically discharge stormwater to the outfall is currently being constructed.

Additionally, the first 1.8 kilometres of the Dome-Kitase Road has been sealed, and the contractor is constructing drains along the remaining stretch of the road. 

The road is expected to be completed by June 2020.

 

Source: Classfmonline.com